中文
Home / IC News

Multiple Semiconductor Manufacturing Projects Delayed in the U.S.

-advertisement-

Recently, despite over USD 400 billion in tax incentives, loans, and subsidies provided by the U.S. under the Inflation Reduction Act and the CHIPS and Science Act to boost local clean energy technology and semiconductor industries, the resurgence of U.S. manufacturing has been delayed as investors hit pause on their plans.

Reportedly, there are 114 major projects tied to these acts, totaling USD 227.9 billion in investments. However, projects with a combined investment of approximately USD 84 billion have faced delays ranging from two months to several years, with some even indefinitely postponed. These delays include several semiconductor projects.

Companies involved have cited worsening market conditions, slowing demand, and uncertainties in domestic policies as reasons for altering their investment plans.

  • TSMC Delays Production at Arizona Facility

On August 13, TSMC announced several board resolutions, including the approval of a nearly USD 29,6 billion capital budget. Among these, TSMC approved up to USD 7.5 billion in funding for its wholly-owned subsidiary, TSMC Arizona.

TSMC had initially planned to build three fabs in Arizona over the next few years, with a total investment of USD 65 billion. However, per a recent New York Times report, despite four years having passed since the announcement, the Arizona plant has yet to produce a single chip.

When TSMC announced plans to build a semiconductor fab in Arizona in May 2020, the initial plan was to start construction in 2021, with production slated to begin in 2024. The second fab was announced in December 2020, with a production target of 2026.

In May of this year, TSMC’s website indicated that the first Arizona fab’s production start has been postponed to the first half of 2025, while the second fab’s production has been delayed to 2028.

As for the third fab, TSMC has not yet disclosed the start date for construction, but the official plan is to commence production by the late 2030s.

  • Intel Delays Construction of Ohio Project

Intel, the U.S. semiconductor manufacturer, plans to invest USD 100 billion over the next five years in new fabs and expansions across Arizona, New Mexico, Ohio, and Oregon, creating 10,000 manufacturing jobs and 20,000 construction jobs.

Yet, according to a previous report by The Wall Street Journal in February, Intel has delayed its USD 20 billion chip project in Ohio due to market downturns and delays in U.S. subsidies.

Intel is set to build two new advanced fabs in Ohio, with an initial plan to begin chip manufacturing in 2025. Following adjustments, the completion of Intel’s Fab1 and Fab2 projects in Ohio has been postponed to 2026–2027, with operations expected to commence around 2027–2028.

  • Samsung Delays Taylor Fab Project

Initially, Samsung planned to build a semiconductor cluster in Taylor, Texas, including two advanced logic fabs and one advanced packaging facility, with up to USD 6.4 billion in U.S. subsidies.

The first of these fabs in Taylor began construction in 2022, initially scheduled to start production in 2024 with 4nm process capabilities. However, the plant may not begin operations until 2026, US local media MySA noted. This delay is likely due to a slowdown in the foundry market and delays in the disbursement of U.S. subsidies.

Meanwhile, according to reports from Tom’s Hardware and the Korean media outlet ETnews, with the delay in the construction of the semiconductor plant, Samsung may upgrade the facility’s advanced process technology from 4nm to 2nm.

Editor:Vicky

▼▼▼

Intel sells stake in chip designer Arm Holdings

Huawei close to releasing AI chip to rival nvidia in china

Intel offers Irish employees voluntary severance packages up to €500K

UK antitrust watchdog launches inquiry into Synopsys' $35B Ansys acquisition

Japanese chipmaker aims to build fully automated 2-nm chip fab

TSMC's US factory build faces much bigger challenges than expected

Phone

+86 191 9627 2716
+86 181 7379 0595

Working Hours

8:30 a.m. to 5:30 p.m., Monday to Friday

Copyright © 2023 HuNan Printed Circuit Association of ChinaSite mapPrivacy PolicyPowered by Bontop

Contact Us